Project Fact

Project included a 3 story forum space with multi-level balconies, tiered classrooms, administrative and faculty offices. The Schneider building is connected to the Heller-Brown building.

Brandeis University - The Heller School for Social Policy and Management

Waltham, MA

Project

Schneider Building - Ground up addition to the Heller School.

Size

36,000 sf

Completion

2005

Duration

2 years

Team
Owner
Brandeis University
Architect
Kyu Sung Woo
General Contractor
Bond Brothers
Landscape Architect
Reed Hilderbrand